staging workflow (#26)
* staging workflow: init empty RFC * 0026-staging-workflow: first draft * 0026-staging-workflow: second draft Close https://github.com/vcunat/rfcs/pull/2 * 0026-staging-workflow alternatives: more discussion
This commit is contained in:
parent
13b5084807
commit
56f5acdb4c
1 changed files with 103 additions and 0 deletions
103
rfcs/0026-staging-workflow.md
Normal file
103
rfcs/0026-staging-workflow.md
Normal file
|
|
@ -0,0 +1,103 @@
|
|||
---
|
||||
feature: staging-workflow
|
||||
start-date: 2018-03-05
|
||||
author: Vladimír Čunát (@vcunat)
|
||||
co-authors: Frederik Rietdijk (@FRidh)
|
||||
related-issues:
|
||||
---
|
||||
|
||||
# Summary
|
||||
[summary]: #summary
|
||||
|
||||
Define a new workflow for the `staging` branch that can better accomodate the
|
||||
current and future influx of changes in order to deliver mass-rebuilds faster to
|
||||
master. As part of this new workflow an additional branch, `staging-next`, shall
|
||||
be introduced.
|
||||
|
||||
|
||||
# Motivation
|
||||
[motivation]: #motivation
|
||||
|
||||
The current workflow cannot handle the high amount of mass-rebuilds that are
|
||||
continuously delivered, resulting in long delays for these deliveries to reach
|
||||
`master`. When a certain delivery causes failures, attemps are typically made to
|
||||
fix these failures and stabilize `staging` so that the specific delivery can still
|
||||
reach `master`.
|
||||
|
||||
Often it happens that during this period of stabilization other mass-rebuilds
|
||||
are submitted, and it is not uncommon that these also introduce failures, thus
|
||||
again increasing the time it takes for a delivery to reach `master`. This is
|
||||
especially worrysome in case of security fixes that need to be delivered as soon
|
||||
as possible.
|
||||
|
||||
# Detailed design
|
||||
[design]: #detailed-design
|
||||
|
||||
There shall be the following branches:
|
||||
- `master` is the main branch where all small deliveries go;
|
||||
- `staging` is branched from `master` and mass-rebuilds and other large deliveries go to this branch;
|
||||
- `staging-next` is branched from `staging` and only fixes to stabilize and security fixes shall be delivered to this branch. This branch shall be merged into `master` when deemed of sufficiently high quality.
|
||||
|
||||
Binary packages shall be build by Hydra for each of these branches. The
|
||||
following table gives an overview of the branches, the check interval in hours,
|
||||
amount of shares, and the jobset that they build.
|
||||
|
||||
|
||||
| Branch | Interval | Shares | Jobset
|
||||
|----------------|----------|--------|-----------
|
||||
| `master` | 4 | High | release.nix
|
||||
| `staging-next` | 12 | Medium | release.nix
|
||||
| `staging` | 6 | Medium | release-small.nix
|
||||
|
||||
|
||||
The check interval of `staging-next` is reduced from 24 hours (the current value
|
||||
for `staging`) to 12 hours. This can be done because only stabilization fixes
|
||||
shall be submitted and thus fewer rebuilds shall typically have to be performed.
|
||||
|
||||
The `staging` branch shall have a short interval of only 6 hours. This is because
|
||||
of the relatively small jobset, and to obtain a higher resolution to detect any
|
||||
troublesome deliveries.
|
||||
|
||||
# Drawbacks
|
||||
[drawbacks]: #drawbacks
|
||||
|
||||
A potential drawback of this new workflow is that the additional branch may be
|
||||
considered complicated and/or more difficult to work with. However, for most
|
||||
contributors the workflow will remain the same, that is, choose `master` or
|
||||
`staging` depending on the number of rebuilds.
|
||||
|
||||
# Alternatives
|
||||
[alternatives]: #alternatives
|
||||
|
||||
## Maintain the status quo
|
||||
|
||||
The current situation could be kept, however, that would not solve any of the
|
||||
issues mentioned in the "Motivation" section.
|
||||
|
||||
## Single branch
|
||||
|
||||
Instead of multiple branches only a single branch, say `master`, could be kept
|
||||
for development. While this removes the issue of merge conflicts, it will result
|
||||
in continuous mass-rebuilds on `master`, slowing down the delivery of binary
|
||||
substitutes and thus development.
|
||||
|
||||
## Reduce Hydra jobset size
|
||||
|
||||
Reducing the size of the Hydra jobset would mean the iteration pace could be
|
||||
higher, but has the downside of testing fewer packages, and having fewer binary
|
||||
substitutes available.
|
||||
|
||||
The part about fewer binary substitutes could be partially mitigated by adding
|
||||
another slower larger jobset that wouldn't block the channel.
|
||||
|
||||
# Unresolved questions
|
||||
[unresolved]: #unresolved-questions
|
||||
|
||||
- The exact amount of shares, which is something that has the be found out.
|
||||
|
||||
# Future work
|
||||
[future]: #future-work
|
||||
|
||||
- Document the new workflow;
|
||||
- Create the new branch;
|
||||
- Create a Hydra jobset for the new branch and adjust the existing jobs.
|
||||